HIGHWAY RULING

Himachal HC orders interest on delayed NH-72 compensation

The case concerns land acquired for the Paonta Sahib–Ballupur bypass in Sirmaur.

⚡ Fuelprice

THE DELAY

Compensation was deposited after 367 days

367 DAYS

The reported gap ran from the 14 February 2022 award to the 16 February 2023 deposit.

⚡ Fuelprice

COURT DIRECTION

Interest set at 7.5% per year

7.5%

The rate applies to the amount payable to the two petitioners for the delayed period.

⚡ Fuelprice

COMPLIANCE

Authorities have two weeks to deposit interest

2 WEEKS

The reported order sets a higher 18% rate from the order date if payment is missed.

⚡ Fuelprice

DRIVER IMPACT

No new toll or FASTag charge announced

The case is about land compensation, so travellers should watch for separate official traffic notices.

⚡ Fuelprice

READ THE FULL STORY

See what the ruling changes

Read the full explainer on compensation, highway work and the road-user takeaway.

⚡ Fuelprice

READ THE FULL STORY

Get the full breakdown

Sources, numbers and what to watch next.

Tap up to read the full article ↑

Read: Himachal HC orders 7.5% interest on delayed NH-72 land compensation